Sunday, January 25, 2015

TODO ASENSO?

TODO ASENSO?


Is the opposite happening? Upper picture shows the construction of Marianos Bridge, Numancia, Aklan. The billboard states the name of the company constructing the bridge, being implemented by DPWH, Region VI, Iloilo City at a contract cost of Php 13.4 million. The project duration is 100 calendar days which was started on June 23, 2014.

However, after almost seven months or 210 days today the construction is estimated 20 percent completed. The Todo Asenso maybe reversed as the construction is very very slow. 

The lower picture shows Kalibo-Numancia Bridge Construction, another symbol of Todo Asenso but the construction is going slow. /MP

1 comment:

URGENT LOAN OFFER WHATSAPP +918929509036 said...

Are you in need of a loan? Do you want to pay off your bills? Do you want to be financially stable? All you have to do is to contact us for more information on how to get started and get the loan you desire. This offer is open to all that will be able to repay back in due time. Note-that repayment time frame is negotiable and at interest rate of 3% just email us (creditloan11@gmail.com)